top of page

FCI Contracting Charges Guide 2025

  • Writer: Association of Farm Contractors Ireland
    Association of Farm Contractors Ireland
  • Apr 17
  • 4 min read

ree



These are the average guideline charges surveyed from FCI members, the actual prices may vary considerably between regions, soil types, distance travelled, size of contract undertaken, size and type of equipment used, amount of product applied etc. FCI is also aware that many contractors make individual arrangements with their client farmers regarding diesel (eg separate fuel surcharge, fuel used on-farm etc). The guide charges below do not reflect this market trend and such agreements may make a significant difference to contracting charges.


Prices are shown as GUIDE ONLY, PLUS VAT at 13.5% and per area or per hour & include operator, unless otherwise stated ©FCI 2025



CONTRACTING OPERATION

 (All Charges in euro EXCLUDING VAT at 13.5%)

 (All Charges in euro  INCL. VAT at 13.5%)

Baling & Bale Handling

 

 

Bale, wrap, stack and move (inc. plastic 4 layers, extra layers additional cost) For NRF add €1/bale

22-24/bale

25-27/bale

Bale, wrap, stack and move (excl. plastic) 

15-16/bale

17-18/bale

Bale and wrap (inc. plastic 4 layers, extra layers additional cost)   For NRF add €1/bale

15-16/bale

16-18/bale

Bale and wrap including combinations (excl. plastic)

11-13/bale

13-15/bale

Baling silage (4 x 4) 

8.50-9/bale

9.50-10/bale

Wrap (4x4) (excl. plastic) 

4-4.50/bale

4.50-5/bale

Bale Transport

82-87/hr or 6/bale

93-99/hr or 6.50/bale

Bale Stacking 

82-87/hr 

93-99/hr

Large square bales of silage (6x4x3) 

17-18/bale

19-20.50/bale

Large 5x3x2 silage bales wrapped 

12-13/bale

14-15/bale

Hay - small square bales 

2/bale

2.50/bale

Hay - round bales (4x4) 

7-8/bale

8-9/bale

Hay - cutting/mowing 

27-28/ac

30-32/ac

Hay - turning/rowing/rowing 

13-15/ac

15-17/ac

Straw - small square bales 

2/bale

2.50/bale

Straw - round bales (4x4) 

7-8/bale

8-9/bale

Straw - round bales (5x4) 

7-8/bale

8-9/bale

Straw - (8x4x3) 

12.50-15/bale

14-17/bale

Straw - (6x3x3) 

8-9/bale

9-10/bale

Straw - (8x3x3) 

10.50-12/bale

12-13.50/bale

 

 

 

Cultivations

 

 

Min till cultivation (per pass) 

38-40/ac

43-45/ac

Disc Harrowing

38/ac/run or 130/hr

43/ac/run or 148/hr

Ploughing - lea 

54-56/ac

61-64/ac

Ploughing - stubble 

50-52/ac

56-59/ac

Power harrowing/run (3m)

56/ac/run or 156/hr

64/ac/run or 177/hr

Rolling 

15/ac or 63/hr

17/ac or 70/hr

Sub-soiling /Mole draining/hr

147-157/hr

168-178/hr

Gravel Mole Drainage

16/ton gravel or 155/ac

18/ton gravel or 175/ac

 

 

 

Drilling/Sowing Operations

 

 

Conventional grain/fertiliser 

52-56/ac

59-64/ac

Conventional seed only 

44-48/ac

49-54/ac

Direct drill 

60-63/ac

68-71/ac

Maize seeding (inc. laying plastic and spraying, excl plastic cost)

95-100/ac

107-113/ac

One pass - seed only 

53-57/ac

60-65/ac

One pass - seed and fertiliser drill 

58-63/ac

65-70/ac

Strip-Till Drill

50/ac

55/ac

Non-Till Disc Drill 

52-54/ac

59-61/ac

One-pass grass reseeding 

63-67/ac

71-76/ac

Grass seeding -quality job, seeding & rolling (not incl. seed)

262 -267/ac

295 -300/ac

Plough, till & sow maize

240-260/ac

270-295/ac

 

 

 

Seed Cleaning & Crimping

 

 

Cleaned and dressed 

183-187/tonne

207-212/tonne

Crimping

17-19/tonne

19-21/tonne

 

 

 

Complete Cultivation Work

 

 

Plough and one pass 

92-100/ac

104-113/ac

Plough, till and sow grain 

110-114/ac

125-130/ac

 

 

 

Fertilizer Application

 

 

Broadcasting - 2 bags per acre 

47/tonne or 100/hour

53/tonne or 113/hour

Broadcasting - general 

47/tonne or 100/hour

53/tonne or 113/hour

Bulk spreading 

47/tonne or 100/hour

53/tonne or 113/hour

Lime spreading 

9-11/tonne

10-12/tonne

 

 

 

Spraying

 

 

Low volume - 83 l/ac 

13-15/ac

15-17/ac

Liquid Nitrogen - per hour

94/hour

115/hour

 

 

 

Combining & Beet 

 

 

Cereals & Oil Seed Rape

70-75/ac

80-85/ac

Cereals & Oil Seed Rape & Chopping

81-86/ac

92-98/ac

Grain transport (up to 15 kilometres) 

10-12/tonne

11-13.50/tonne

Beet harvesting

162-168/ac

184-190/ac

 

 

 

Hedgecutting

 

 

Hedgecutter - flail 

65-70/hr

74-80/hr

Hedgecutter - sawhead 

82-87/hr

93-99/hr

Hedgecutter - excavator/digger

87-90/hr

99-102/hr

Mulching hedges

87-96/hr

99-110/hr

 

 

 

Silage & Willow Harvesting

 

 

Mowing - conditioner 

27-28/ac

30-32/ac

Raking/Tedding/Rowing

15.50-17/ac

17.50-19.50/ac

Precision chop grass silage - complete job (in pit) 

168-178/ac (extra for long draw)

190-200/ac (extra for long draw)

Maize silage  - complete job (in pit) 

192-197/ac (extra for long draw)

218-224/ac (extra for long draw)

Wagon silage  - complete job (into the pit) 

157-168/ac (extra for long draw)

178-190/ac (extra for long draw)

Whole crop silage - complete job (into the pit)

184-189/ac (extra for long draw)

208-214/ac (extra for long draw)

Samco Silage Bagging

27/linear metre

30/linear metre

Zero Grazing

87-97/load (will vary with capacity & distance)

99-110/load (will vary with capacity & distance)

Willow harvesting complete job

230/ac (extra for long draw)

262/ac (extra for long draw)

Topping Grassland

23/ac or 60/hour

26/ac or 68/hour

 

 

 

Slurry & Muck Spreading

 

 

Muck loading wheeled loader

70-75/hr

80-85/hr

Muck spreading - flail 

63-65/hr

71-74/hr

Muck spreading - 10 tonne 

70-80/hr

79-90/hr

Muck spreading - 14 tonne 

94-105/hr

107-120/hr

Loading and spreading - 12 tonne spreader

145-150/hr

164-170/hr

14 tonne dual/rear discharge spreader and loader 

163-172/hr

185-195/hr

Slurry agitation 

105-125/hr

119-140/hr

Slurry spreading - 1500 gal tanker 

70-75/hr

79-85/hr

Slurry spreading - 2500 + gal tanker 

76-86/hr

86-98/hr

Slurry spreading - 3000 + gal tanker 

102-109/hr

116-124/hr

Umbilical spreading (set up charge - laying out & reeling in €100/hr)

168-178/hr

190-202/hr

Dribble Bar - 2500 + gal tanker 

92-97/hr

105-110/hr

Trailing Shoe - 2500 + gal tanker 

97-109/hr

110-124/hr

 

 

 

Plant & Tractor Hire & Snow Work

 

 

14t excavator 

90/hr

100/hr

Digger hire (3CX) 

71-73/hr

80-83/hr

Tractor and dumper - 14 tonne 

71-81/hr

87-99/hr

Wheel Loader - 10 tonne 

87-97/hr

99-110/hr

Teleporter

71-73/hr

81-83/hr

Mini - digger 

40-44/hr

44-49/hr

Road sweeper 

66-68/hr

75-77/hr

Tractor Hire (100 to 150hp tractor & operator)

63-65/hr

71-74/hr

Tractor Hire (150 to 200hp tractor & operator)

74-78/hr

83-89/hr

Tractor Hire (200hp to 250hp tractor & operator)

82-87/hr

93-99/hr

Wheel Loader Snow Hire - 10 tonne 

100-120/hr

113-135/hr

Tractor Snowplough Hire (100 to 150hp tractor & operator)

88-98/hr

100-110/hr

Tractor Snowplough Hire (150 to 200hp tractor & operator)

103-113/hr

116-128/hr

Digger hire (3CX) at snow work

82-87/hr

93-99/hr

 

 

 

Forestry Contracting

 

 

Forwarded Small

96-115/hr

110-130/hr

Forwarded Large

130-136/hr

147-155/hr

Timber Harvester Small

136-147/hr

155-168/hr

Timber Harvester Large

147-168/hr

166-190/hr


Comments


bottom of page